Modular Frame Office

This modular office was lifted into place and was positioned on our commercial ground screws to enable this location to be quickly transformed a fully functional office unit.

The challenge

This modular office was being situated in a rural location where the use of concrete wasn’t an option. With services running through the installation area and a stipulation that no permanent damage could be made to the site, our Ground Screws became solution to meet the client requirements.

The solution

Our team coordinated with the landowner, the modular office sales and installation team, offering a comprehensive solution to facilitate the installation of this office. We organised a GPR survey to detect any underground services and carried out a compression load test before the installation of our 76mm diameter Commercial Ground Screws. This enabled the office to be lifted into position section by section and caused no disruption to the operations of neighbouring businesses. It was all part of a day’s work for the GSCUK team.